Steven...Another point...when I worked at Boeing....I was enlightened as to the process within the Engineering section.
When a change was contemplated by an airline....it was submitted to a "change Board"....where all invovled met to discuss the change. I recall, that when there was a "lead' time of several weeks to a month in getting the vendor supplying a part, to get the part to the Receiving Dock..then the part had to go through Quality inspection to make sure the part met the blueprint specs. When all agreed, it might be several aircraft down the assembly line. before the change could be accomplished.
In addition, the Engineering drawings had to be brought up to date, with the change for that airline.
Boeing, when it came to a new airplane...take the new 787 as an example....the FIRST airline that buys the 787, ....it, no longer is Boeing...it becomes that airline's aircraft, with all that airline's specs.
When a new customer also buys a 787, where the numbering system of the Engineering Drawing, is all numbers, the new customer has an "A" suffix added to the Drawing, when the next new customer, wants someing different from either the original customer, and the second customer, it's drawings get a "B" suffix.
At the mfg level, when a part is mfg for customer "B" then the specs and drawings reflect that airlines specs.
An example would be in the radios....the original customer requested Collins radios...the second customer requested Bendix,then the drawing number for the original customer would have straight numbers, the second customer would have a "A" sufffix, etc.
Each time, the respective drawings would have to have the Engineering Group bring the Drawings up to date, so that the correct customer's drawings could be used to mfg the part.
When it came to "spares" the tooling jigs were stored at Kent Washington with the main plant at Renton, WA, some 20-30 miles from the assembly at Renton.
The Shop where the part was mfg, had to have the current tooling jigs set aside, and the spares tooling installed (temporarily), the necessary parts mfg, and the tooling jigs then returned to the storage area, and the current tooling and jigs reinstalled.
After my brother related that his TWA 707 came back from Europe, it had an EL AL rudder with the EL AL paint.
A person at Boeing, was wondering why one airline ordered nothing but rudders, another ordered nothing but landing flaps, etc. My brother explained that each of the airlines operating the same aircraft, would store certain parts, and when one of the participating airlines needed a part, it was available, ( In Europe),
and each airline, thus was not required to each store parts for an entire aircraft.
I hope this explains some of the problems and how some were solved, at Boeing.
Jim :-)